SUPERVISING AUTHORITY

Antea Cement Sh.a. (TITAN)

CONTRACT DATE

16/02/2009

COMPLETION DATE (last updated)

31/12/2009

CONTRACT BUDGET  (€) (WITHOUT VAT/ WITH VAT)

992.491,15/ 1.190.989,38

COMPLETED PROJECT BUDGET (€) (WITHOUT VAT/ WITH VAT)

49.098,81/58.918,57

UPDATED PROJECT COST (€) (WITHOUT VAT/ WITH VAT)

-/-

Antea Cement Sh.a. (TITAN)

SUPERVISING AUTHORITY

EMPORIKI BANK

CONTRACT DATE

20/02/2009

COMPLETION DATE

01/05/2009

CONTRACT BUDGET  (€) (WITHOUT VAT/ WITH VAT)

140.000,00 / 166.600,00

COMPLETED PROJECT BUDGET (€) (WITHOUT VAT/ WITH VAT)

140.000,00 / 166.600,00

UPDATED PROJECT COST (€) (WITHOUT VAT/ WITH VAT)

-/-

Emporiki Bank

SUPERVISING AUTHORITY

TERNA S.A.

CONTRACT DATE

22/11/2008

COMPLETION DATE (last updated)

31/10/2009

CONTRACT BUDGET  (€) (WITHOUT VAT/ WITH VAT)

1.253.656.20/1.504.387,44

COMPLETED PROJECT BUDGET (€) (WITHOUT VAT/ WITH VAT)

641.687,53/770.025,04

UPDATED PROJECT COST (€) (WITHOUT VAT/ WITH VAT)

-/-

PHOTOS

SUPERVISING AUTHORITY

ORTHODOXE CHURCH OF ALBANIA

CONTRACT DATE

20/06/2008

COMPLETION DATE

15/10/2009

CONTRACT BUDGET  (€) (WITHOUT VAT/ WITH VAT)

365.000,00 / 434.350,00

COMPLETED PROJECT BUDGET (€) (WITHOUT VAT/ WITH VAT)

266.000,00 / 316.540,00

UPDATED PROJECT COST (€) (WITHOUT VAT/ WITH VAT)

-/-

SUPERVISING AUTHORITY

PATOS PETROL

CONTRACT DATE

14-07-2004

COMPLETION DATE

 

CONTRACT BUDGET  (€) (WITHOUT VAT/ WITH VAT)

19.166,66/ 23.000,00

COMPLETED PROJECT BUDGET (€) (WITHOUT VAT/ WITH VAT)

9.260,00/ 11.019,40

UPDATED PROJECT COST (€) (WITHOUT VAT/ WITH VAT)

-/-

PATOS PETROL
Project is stopped.

SUPERVISING AUTHORITY

TECHNICAL SERVICES OF EUROPEAN UNION

CONTRACT DATE

11-02-2005

COMPLETION DATE

-

CONTRACT BUDGET  (€) (WITHOUT VAT/ WITH VAT)

 45.833,33/ 55.000,00

COMPLETED PROJECT BUDGET (€) (WITHOUT VAT/ WITH VAT)

 45.833,33/ 55.000,00

UPDATED PROJECT COST (€) (WITHOUT VAT/ WITH VAT)

-/-

GENERAL CARS

SUPERVISING AUTHORITY

MT CONSTRUCTION

CONTRACT DATE

05-01-2005

COMPLETION DATE

 

CONTRACT BUDGET  (€) (WITHOUT VAT/ WITH VAT)

61.630,00/ 73.956,00

COMPLETED PROJECT BUDGET (€) (WITHOUT VAT/ WITH VAT)

61.630,00/ 73.956,00

UPDATED PROJECT COST (€) (WITHOUT VAT/ WITH VAT)

-/-

MT CONSTRUCTION

SUPERVISING AUTHORITY

 

CONTRACT DATE

27-09-2004

COMPLETION DATE

 

CONTRACT BUDGET  (€) (WITHOUT VAT/ WITH VAT)

55.833,33/ 67.000,00

COMPLETED PROJECT BUDGET (€) (WITHOUT VAT/ WITH VAT)

55.833,33/ 67.000,00

UPDATED PROJECT COST (€) (WITHOUT VAT/ WITH VAT)

-/-

SUPERVISING AUTHORITY

 

CONTRACT DATE

23-03-2004

COMPLETION DATE

 

CONTRACT BUDGET  (€) (WITHOUT VAT/ WITH VAT)

25.000,00/ 30.000,00

COMPLETED PROJECT BUDGET (€) (WITHOUT VAT/ WITH VAT)

1.575,00/ 1.890,00

UPDATED PROJECT COST (€) (WITHOUT VAT/ WITH VAT)

-/-

Project is stopped.

SUPERVISING AUTHORITY

MT CONSTRUCTION

CONTRACT DATE

16-03-2004

COMPLETION DATE

-

CONTRACT BUDGET  (€) (WITHOUT VAT/ WITH VAT)

7.300,00/ 8.760,00

COMPLETED PROJECT BUDGET (€) (WITHOUT VAT/ WITH VAT)

-/-

UPDATED PROJECT COST (€) (WITHOUT VAT/ WITH VAT)

-/-

MT CONSTRUCTION
Project is stopped.

SUPERVISING AUTHORITY

“GJIKURIA” SH.P.K

CONTRACT DATE

23-04-2002

COMPLETION DATE

-

CONTRACT BUDGET  (€) (WITHOUT VAT/ WITH VAT)

102.794.00/ 123.353,58

COMPLETED PROJECT BUDGET (€) (WITHOUT VAT/ WITH VAT)

102.794.00/ 123.353,58

UPDATED PROJECT COST (€) (WITHOUT VAT/ WITH VAT)

-/-

SUPERVISING AUTHORITY

RIVIERA SH.P.K.

CONTRACT DATE

18-10-2002

COMPLETION DATE

-

CONTRACT BUDGET  (€) (WITHOUT VAT/ WITH VAT)

8.389,16/ 10.067.00

COMPLETED PROJECT BUDGET (€) (WITHOUT VAT/ WITH VAT)

8.389,16/ 10.067.00

UPDATED PROJECT COST (€) (WITHOUT VAT/ WITH VAT)

-/-

SUPERVISING AUTHORITY

TIRANA ARCHBISHOPY

CONTRACT DATE

27-07-2002

COMPLETION DATE

-

CONTRACT BUDGET  (€) (WITHOUT VAT/ WITH VAT)

13.248,30/ 15.632.99

COMPLETED PROJECT BUDGET (€) (WITHOUT VAT/ WITH VAT)

13.248,30/ 15.632.99

UPDATED PROJECT COST (€) (WITHOUT VAT/ WITH VAT)

-/-

SUPERVISING AUTHORITY

WORLD BANK

CONTRACT DATE

01-11-2002

COMPLETION DATE

-

CONTRACT BUDGET  (€) (WITHOUT VAT/ WITH VAT)

41.282,97/ 49.539,56

COMPLETED PROJECT BUDGET (€) (WITHOUT VAT/ WITH VAT)

41.282,97/ 49.539,56

UPDATED PROJECT COST (€) (WITHOUT VAT/ WITH VAT)

-/-

“DIEKAT NDERTIM CONSTRUCTION”

SUPERVISING AUTHORITY

ARAL SH.P.K.

CONTRACT DATE

02-06-2003

COMPLETION DATE

-

CONTRACT BUDGET  (€) (WITHOUT VAT/ WITH VAT)

14.783,33/ 17.740,00

COMPLETED PROJECT BUDGET (€) (WITHOUT VAT/ WITH VAT)

14.783,33/ 17.740,00

UPDATED PROJECT COST (€) (WITHOUT VAT/ WITH VAT)

-/-

SUPERVISING AUTHORITY

EDAL SH.P.K.

CONTRACT DATE

31-07-2003

COMPLETION DATE

-

CONTRACT BUDGET  (€) (WITHOUT VAT/ WITH VAT)

8.750,00/ 10.500,00

COMPLETED PROJECT BUDGET (€) (WITHOUT VAT/ WITH VAT)

8.750,00/ 10.500,00

UPDATED PROJECT COST (€) (WITHOUT VAT/ WITH VAT)

-/-

SUPERVISING AUTHORITY

MINISTRY OF EDUCATION

CONTRACT DATE

19-05-2003

COMPLETION DATE

-

CONTRACT BUDGET  (€) (WITHOUT VAT/ WITH VAT)

15.900,00/ 24.960,00

COMPLETED PROJECT BUDGET (€) (WITHOUT VAT/ WITH VAT)

15.900,00/ 24.960,00

UPDATED PROJECT COST (€) (WITHOUT VAT/ WITH VAT)

-/-

ALBA CONSTRUCTION SH.P.K.

SUPERVISING AUTHORITY

MINISTRY OF HEALTH

CONTRACT DATE

19-05-2003

COMPLETION DATE

-

CONTRACT BUDGET  (€) (WITHOUT VAT/ WITH VAT)

16.666,67/ 20.000,00

COMPLETED PROJECT BUDGET (€) (WITHOUT VAT/ WITH VAT)

16.666,67/ 20.000,00

UPDATED PROJECT COST (€) (WITHOUT VAT/ WITH VAT)

-/-

LALA SH.P.K.

SUPERVISING AUTHORITY

MINISTRY OF WORKS

CONTRACT DATE

11-03-2005

COMPLETION DATE

-

CONTRACT BUDGET  (€) (WITHOUT VAT/ WITH VAT)

11.666,66/ 14.000,00

COMPLETED PROJECT BUDGET (€) (WITHOUT VAT/ WITH VAT)

11.666,66/ 14.000,00

UPDATED PROJECT COST (€) (WITHOUT VAT/ WITH VAT)

-/-

SAN TARA SH.P.K.

SUPERVISING AUTHORITY

MAPA NDERTIM & TREGETI SH.A.

CONTRACT DATE

06-10-2003

COMPLETION DATE

 

CONTRACT BUDGET  (€) (WITHOUT VAT/ WITH VAT)

8.333,33/ 10.000,00

COMPLETED PROJECT BUDGET (€) (WITHOUT VAT/ WITH VAT)

8.333,33/ 10.000,00

UPDATED PROJECT COST (€) (WITHOUT VAT/ WITH VAT)

-/-

MAPA NDERTIM & TREGETI SH.A.

SUPERVISING AUTHORITY

CONTRACT DATE

01-06-2004

COMPLETION DATE

 

CONTRACT BUDGET  (€) (WITHOUT VAT/ WITH VAT)

18.750,00/ 22.500,00

COMPLETED PROJECT BUDGET (€) (WITHOUT VAT/ WITH VAT)

18.750,00/ 22.500,00

UPDATED PROJECT COST (€) (WITHOUT VAT/ WITH VAT)

-/-

SUPERVISING AUTHORITY

ALUMIL ALBANIA

CONTRACT DATE

16-03-2004

COMPLETION DATE

-

CONTRACT BUDGET  (€) (WITHOUT VAT/ WITH VAT)

82.920,18/ 99.504,22

COMPLETED PROJECT BUDGET (€) (WITHOUT VAT/ WITH VAT)

82.920,18/ 99.504,22

UPDATED PROJECT COST (€) (WITHOUT VAT/ WITH VAT)

-/-

MT CONSTRUCTION

SUPERVISING AUTHORITY

LOULIS S.A.

CONTRACT DATE

26-04-2004

COMPLETION DATE

-

CONTRACT BUDGET  (€) (WITHOUT VAT/ WITH VAT)

11.305,00/ 13.566,00

COMPLETED PROJECT BUDGET (€) (WITHOUT VAT/ WITH VAT)

11.305,00/ 13.566,00

UPDATED PROJECT COST (€) (WITHOUT VAT/ WITH VAT)

-/-

‘DIEKAT NDERTIM CONSTRUCTION’

SUPERVISING AUTHORITY

PETCOR INTERNATIONAL

CONTRACT DATE

19-03-2004

COMPLETION DATE

-

CONTRACT BUDGET  (€) (WITHOUT VAT/ WITH VAT)

6.080,00/ 7.296,00

COMPLETED PROJECT BUDGET (€) (WITHOUT VAT/ WITH VAT)

6.080,00/ 7.296,00

UPDATED PROJECT COST (€) (WITHOUT VAT/ WITH VAT)

-/-

‘DIEKAT NDERTIM CONSTRUCTION’

SUPERVISING AUTHORITY

KRISTIAN CONSTRUCTION

CONTRACT DATE

23-12-2003

COMPLETION DATE

-

CONTRACT BUDGET  (€) (WITHOUT VAT/ WITH VAT)

36.875,00/ 44.250,00

COMPLETED PROJECT BUDGET (€) (WITHOUT VAT/ WITH VAT)

35.208,33/ 42.250,00

UPDATED PROJECT COST (€) (WITHOUT VAT/ WITH VAT)

-/-

KRISTIAN CONSTRUCTION

SUPERVISING AUTHORITY

INTRALBAN SH.A.

CONTRACT DATE

22-06-2004

COMPLETION DATE

-

CONTRACT BUDGET  (€) (WITHOUT VAT/ WITH VAT)

12.917,00/ 15.500,00

COMPLETED PROJECT BUDGET (€) (WITHOUT VAT/ WITH VAT)

12.917,00/ 15.500,00

UPDATED PROJECT COST (€) (WITHOUT VAT/ WITH VAT)

-/-

INTRALBAN SH.A.

SUPERVISING AUTHORITY

MINISTRY OF EDUCATION

CONTRACT DATE

27-09-2004

COMPLETION DATE

-

CONTRACT BUDGET  (€) (WITHOUT VAT/ WITH VAT)

31.200,00/ 37.440,00

COMPLETED PROJECT BUDGET (€) (WITHOUT VAT/ WITH VAT)

31.505,16/ 37.806,19

UPDATED PROJECT COST (€) (WITHOUT VAT/ WITH VAT)

-/-

MURATI SH.P.K.

SUPERVISING AUTHORITY

VODAFONE ALBANIA

CONTRACT DATE

 

COMPLETION DATE

 

CONTRACT BUDGET  (€) (WITHOUT VAT/ WITH VAT)

42.266,67/ 50.720,00

COMPLETED PROJECT BUDGET (€) (WITHOUT VAT/ WITH VAT)

42.266,67/ 50.720,00

UPDATED PROJECT COST (€) (WITHOUT VAT/ WITH VAT)

-/-

‘DIEKAT NDERTIM CONSTRUCTION’

SUPERVISING AUTHORITY

EDRI SH.P.K.

CONTRACT DATE

12-07-2004

COMPLETION DATE

-

CONTRACT BUDGET  (€) (WITHOUT VAT/ WITH VAT)

10.489,92/ 12.587,00

COMPLETED PROJECT BUDGET (€) (WITHOUT VAT/ WITH VAT)

10.489,92/ 12.587,00

UPDATED PROJECT COST (€) (WITHOUT VAT/ WITH VAT)

-/-

EDRI SH.P.K.